中/EN

Hangzhou Xinkai Transmission Machinery Co., Ltd. New Workshop Project Environmental Impact Assessment Publicity

发布日期:2018-07-11 浏览量:2004

Hangzhou Xinkai Transmission Machinery Co., Ltd. New Workshop Project Environmental Impact Assessment Publicity I. Basic Situation of Construction Project


Project Name: New Workshop Project of Hangzhou Xinkai Transmission Machinery Co., Ltd.


 Construction unit: Hangzhou Xinkai Transmission Machinery Co., Ltd.


 Nature of the project: relocation


 Construction site: Gongyu Village, Xinwan Street, Xiaoshan District, Hangzhou


Project construction scale: Hangzhou Xinkai Transmission Machinery Co., Ltd. plans to invest 80 million yuan, 10,516 square meters of newly acquired land (Xinyu Village, Xinwan Street) to build production houses. After the completion of the plant, the existing production line will be relocated to the new factory. The new heat treatment process and equipment will be added. After the relocation, it will form an annual production capacity of 5,000 sets of SWC ships, power propulsion and vibration-reduction strengthening universal joints, and 10,000 sets of military constant-speed drive shafts and universal joints.

2. Distribution of major environmentally sensitive targets within the scope of environmental impact assessment

The main environmentally sensitive target within the scope of project evaluation is the south side of Gongyu Village (the closest distance from the factory boundary is about 16m).

Third, the main environmental impact prediction

Ambient air impact: The waste gas of this project is mainly the non-methane total hydrocarbon produced by the heat treatment process. The enterprise's heat treatment organic waste gas emission meets the “New Pollutant Emission Limit Level 2” standard and other corresponding standards requirements of the “Integrated Emission Standard for Air Pollutants” (GB16297-1996). The maximum floor concentration and rate of the project's exhaust gas are small, meeting the corresponding standard requirements, and have little impact on the surrounding atmospheric environment, and do not touch the bottom line of the atmospheric environment quality.

Water environment impact: There is no production wastewater in this project, and the wastewater is mainly domestic sewage of employees. After the canteen wastewater is treated by the grease trap, it is treated with the other domestic sewage through the septic tank to reach the Class III standard of Integrated Wastewater Discharge Standard (GB8978-1990), and then included in the municipal sewage pipe network, and finally discharged into the Linjiang Wastewater Treatment Plant for treatment. On this basis, the project wastewater discharge has little impact on the surrounding water environment and does not touch the water environment quality bottom line.

Acoustic environmental impact: The noise contribution value of the four-year boundary of the project is 50.1-52.4dB(A) when it is normally engaged in production activities, which can meet the requirements of Class 2 standard of Environmental Noise Emission Standard for Industrial Enterprises (GB12348-2008). (Dual 60dB(A)), the noise prediction value of the sensitive point is 56.8dB(A), which can meet the requirements of the Class 2 standard limit of the Acoustic Environmental Quality Standard (GB3096-2008) (60dB in the daytime) (A)). In summary, the noise of this project can be achieved after stable discharge and does not touch the bottom line of acoustic environment quality.

Solid waste impact: The solid waste generated by the project includes industrial solid waste and domestic waste. The industrial solid waste is mainly waste cutting fluid, waste engine oil, waste cleaning agent water, waste quenching oil and scrap. The scraps are collected and sold to the material recovery unit; the waste cutting fluid, waste engine oil, waste cleaning agent water, and waste quenching oil enterprises are entrusted to the qualified units for recycling and disposal; the waste catalyst enterprises are collected and disposed of by the manufacturers; the domestic garbage is sanitation The department unified transportation. In summary, the solid waste generated by the project can be properly solved and the external environment has little impact.

4. Main environmental protection measures to be taken and expected effects

Prevention and control of exhaust gas pollution: The whole heat treatment workshop is sealed with micro-negative pressure. After the exhaust gas is collected, it is discharged by the condensing + high-voltage electrostatic waste gas treatment facility and discharged through the high-altitude exhaust pipe of 15 meters. There is a very small amount of carburized exhaust gas, and this EIA does not do quantitative analysis.Prevention of water pollution: the canteen wastewater is treated by the grease trap and then treated with other domestic sewage through the septic tank to reach the third-level standard of Integrated Wastewater Discharge Standard (GB8978-1990), which is then included in the municipal sewage pipe network and finally discharged into Linjiang sewage. Treatment plant processing.

Noise pollution prevention: All production equipment should use low-noise models, actively adopt vibration reduction and noise reduction measures for high-noise equipment, and take regular inspections on various equipments to ensure that mechanical equipment operates under normal working conditions.Prevention and control of solid waste pollution: After the collection, the scraps are uniformly sold to the material recovery unit; the waste cutting fluid, waste engine oil, waste cleaning agent water, and waste quenching oil enterprises are entrusted to the qualified units for recycling and disposal; the domestic garbage is uniformly cleared by the sanitation department.V. Preliminary conclusions of environmental impact assessmenthe new workshop project of Hangzhou Xinkai Transmission Machinery Co., Ltd. is in line with the relevant national industrial policies, conforms to the ecological protection red line, the environmental quality bottom line, and the resource utilization on-line control requirements, and is not included in the negative list of environmental access. At the same time, the project is in line with the local land use planning, environmental function zoning, and urban development master plan; after taking corresponding measures, the discharged pollutants can be discharged to the standard, and the local environmental quality status can be maintained after the completion, and environmental risk accidents occur to the environment. The impact is within acceptable levels; project construction is in line with public participation requirements and is conducive to promoting the healthy and sustainable development of the local economy.

Therefore, from the perspective of environmental protection, the project only needs to implement the various measures proposed in this EIA, strictly implement the “three simultaneous” formulation, strengthen environmental management, and implement the project.

6. Environmental impact report disclosure method and time

The environmental impact report of this project will be published on the website of the construction unit (http://www.hzxkcd.com/channels/2.html) before being submitted to the competent environmental protection authority for approval.

7. Scope and main issues for public consultationOpinions and suggestions on environmental protection during project implementation.Eight, public feedback channels

The public may, after the relevant information is disclosed, send letters, faxes, e-mails or other means in accordance with the relevant publicity requirements to the construction unit or environmental impact assessment agency, the local environmental protection administrative department, and the environmental protection administrative director responsible for approving the environmental impact report. Department, submit comments. 9. The start and end time of the public's comments

Within 10 working days from the date of publication, the specific time is from July 11, 2018 to July 24, 2018.

X. Situation of local environmental protection departments, environmental assessment units and project construction units

Announcement release unit: Hangzhou Xinkai Transmission Machinery Co., Ltd.


Date: July 11, 2018